Project Development | Management | Facilitation | Integration
At the same time, opportunities exist on the other side of the market. Power plants may be decommissioned, mothballed or otherwise no longer required at their present location, even though they still have considerable technical value and remaining operating life. Instead of being permanently shut down and ultimately demolished, such plants may be available for acquisition and relocation.
A relocation project, however, should not be understood simply as purchasing used equipment, dismantling it and rebuilding it elsewhere. Properly developed, it is a complex techno-commercial project extending from the identification and assessment of a suitable asset through to engineering, dismantling, transportation, rehabilitation, reconstruction and commissioning at a new location.
The attractiveness of this approach is primarily based on two factors: Time and Cost
Consequently, plants offered for relocation can range from completely unused equipment to plants with relatively few operating hours or well-maintained facilities with substantial remaining technical life.
The term “pre-owned” therefore does not automatically mean “old” or “worn out.”
The important question is not simply the age of the plant, but its actual technical condition, operating history, maintainability, remaining lifetime and suitability for the intended new location.
Indicative Comparison of Project Schedules
This schedule advantage can be particularly important where generation capacity is urgently required. Every month by which commercial operation can be advanced can have considerable economic value.
The relevant figure is the total installed and commissioned project cost at the new location.
In addition to the plant purchase price, this typically needs to consider:
Even after these costs are considered, a carefully selected plant may provide a substantial investment advantage compared with a new-build project.
There is also a second important economic effect:
Earlier operation can mean earlier revenue generation.
Illustrating the Potential Economic Benefits
The potential economic benefits can be illustrated by the simplified diagrams below. They show the typical relationship between project investment, implementation time, start of revenue generation and break-even point.
The diagrams illustrate the general principle and potential advantages and should not be regarded as a detailed economic analysis of a specific project.
New Power Plant
A conventional new-build project normally requires a longer development and construction period before the plant starts generating revenue. The capital invested therefore remains tied up for a comparatively long period before the project reaches its break-even point.
Relocated Pre-Owned Power Plant
Figure 3 – Simplified Project Cost and Earnings – Relocated Pre-Owned Power Plant
A relocation project can normally be implemented within a shorter period and with a lower initial investment than a comparable new-build project. As a result, the plant can start generating revenue earlier and the project may reach its break-even point considerably sooner.
New vs. Relocated Pre-Owned Power Plant
Figure 4 – Simplified Project Cost and Earnings – New vs. Relocated Pre-Owned Power Plant
The relocation concept can change the economic profile significantly through a combination of:
The economic comparison should therefore consider not only CAPEX and remaining plant lifetime, but also the time required to reach commercial operation and the resulting break-even point.
The advantages should not obscure the risks.
A technically unsuitable plant purchased at an attractive price can ultimately become an expensive project. The most important decisions are therefore often made before the plant is purchased.
Only after these issues have been adequately assessed can the real value of a pre-owned plant be determined.
Relocation projects differ fundamentally from conventional new-build projects.
A new plant is generally designed around the requirements of the new site. With a relocation project, the starting point is reversed:
An existing technical solution has to be adapted to a new environment.
This makes early technical due diligence, realistic cost and schedule assessment, and effective interface management particularly important.
The process should normally start with a high-level screening of available plants, followed by progressively more detailed technical and commercial assessment. Only plants satisfying the fundamental requirements of the intended project should proceed to detailed inspection, negotiations and acquisition.
The objective is not to find the cheapest available plant. It is to identify the plant offering the best overall techno-commercial fit for the intended project.
Relocation projects can be especially attractive where there is:
In such cases, the shorter implementation time, lower capital requirement and potentially more appropriate remaining operating life of a suitable pre-owned plant may offer a better fit than a completely new installation.
Relocation of pre-owned power plants is not a universal solution to power-generation problems.
But neither should it be regarded simply as a second-best alternative to new equipment.
Under suitable circumstances, a carefully selected and professionally assessed existing plant can provide a technically sound and commercially attractive basis for a fast-track, lower-investment project.
While this article focuses primarily on power generation, the underlying concept is not limited to power plants. Similar opportunities may exist for process plants, refineries, chemical and petrochemical facilities, manufacturing plants and other industrial installations where existing assets can be economically dismantled, relocated, adapted and recommissioned at a new location.
The fundamental principles remain largely the same: identifying a suitable available asset, matching it with the requirements of a new project, assessing its condition and remaining life, evaluating the cost and feasibility of relocation, and developing an appropriate technical and commercial implementation concept.
The decisive factors are the quality of plant selection, the depth of the technical assessment, realistic evaluation of the total relocation cost and schedule, appropriate involvement of OEMs and specialised companies, and effective management of the many interfaces between the existing plant and its new environment.
Ultimately, the question should not be:
“New or used?”
It should be:
“Which solution provides the best combination of investment cost, implementation time, technical risk and required operating life for this particular project?”
A relocation project starts long before dismantling begins. It often starts with two independent opportunities: a requirement for generation capacity on one side and a suitable plant that is no longer required at its present location on the other.
Bringing these opportunities together and developing them into a viable project requires a combination of technical, commercial and project-development expertise.
My particular focus is on the identification, assessment, development, facilitation and structuring of such opportunities, including:
The subsequent relocation and implementation requires expertise across many disciplines, potentially including plant inspection, remaining-life assessment, OEM services, engineering, dismantling, logistics, rehabilitation and upgrading, civil works, construction, commissioning, legal and commercial expertise, and local knowledge at both the existing and future plant locations.
Through cooperation with experienced partners, specialised engineering companies, OEMs and other professional service providers, the necessary expertise can be brought together and tailored to the specific requirements of each project.
The objective is to take a relocation opportunity from an initial idea through plant identification, matching, technical and commercial assessment, project structuring and implementation and develop it into a technically sound, commercially viable and successfully executed project.
To be continued.